On 20th August 2014, Phuket Highways Office Director – Khun Samak Luedwonghad said that the agency has temporarily allowed the use of the new Central Festival underpass to those travelling north due to a problem with the ground level road. Due to the recent heavy rain the road has become unusable due to drainage issues. He advised that the temporary use of the underpass will continue until 31st August.
Unfortunately, people travelling north who wish to turn left into Wichit Songkram Road are currently unable to do so are being advised to use Bang Yai Road instead. However, workers are now repairing the road and removing all waste materials from the area so drivers should be able to turn left into Wichit Songkram Road by next week.
Khun Samak also advised that the project is currently 85% complete and he hoped that all works will be complete come October.